A total of 717 out of 1,091 upgrading and reconstruction projects for dilapidated schools nationwide have been fully completed as of yesterday.
717 Dilapidated Schools Upgraded: MOE Celebrates Milestone
The Ministry of Education (MOE) said that 183 projects are currently under construction, 176 are in the pre-construction phase, and 15 are undergoing re-evaluation.
“The construction timeline for these projects ranges from six to 36 months, depending on the scope of work and site preparation requirements,” it said in a statement.
As of this year, a total of 1,091 school upgrade projects have been approved, with a combined allocation of RM8.5 billion. These include 339 projects in Sabah, 400 in Sarawak, and 352 in Peninsular Malaysia.